Everything you need to know about a typical double glazing project time frame.
The time it takes to complete a project varies, and largely depends on the window or door type being installed.
For an average three-bedroom home with good access, an aluminium reFIT project will often take around 2-3 working days, whereas a Timber reFIT project would often take around 6-7 working days.
When new joinery is being installed, a reFRAME Inner project would often take around 5-6 working days, while full frame replacement projects (reFRAME Full), usually take twice as long. You can read more about these installation services here.
To get started, get in touch with us today by clicking here.